A Daily Drilling Report (DDR) is the official record of what happened on a well over 24 hours. It is sent to the operator's office every morning and is the basis for tracking progress, cost, and problems on the well. For petroleum engineering students, understanding the DDR is a fast way to learn how drilling operations run day to day.

Who writes the DDR

The DDR is usually compiled by the drilling supervisor (often called the company man) with help from the wellsite drilling engineer. The data comes from many people: the rig crew for hourly activities, the mud engineer for mud data, the directional driller for surveys, and the mud logger for depth and gas data.

The usual structure of a DDR

Every company has its own format, but the content almost always includes the following sections.

SectionContent
HeaderWell name, rig, report number, date, days from spud, MD and TVD
24-hour summaryA short summary of the work completed
Time breakdownActivities per time period with operation codes and depths
NPTNon-productive time, its cause, and its duration
Mud dataDensity, viscosity, PV, YP, filtrate, and volume
BHA and bitsBottom hole assembly, rotating hours, and bit condition
SurveysDepth, inclination, and azimuth
HSE and personnelPeople on site, incidents, and safety drills
24-hour planWork planned for the next day

Writing the time breakdown properly

The time breakdown is the most-read part of the report. The basic rules are simple: durations must add up to exactly 24 hours, every line has an operation code, and start and end depths are recorded for activities that make hole.

TimeCodeDescription
00:00–06:00DRLDrill 8½ in hole from 2,512 m to 2,590 m
06:00–07:00CIRCCirculate bottoms up before survey
07:00–07:30SRVSurvey at 2,585 m, inclination 38.4°
07:30–09:00NPTTop drive repair
09:00–12:00DRLDrill 8½ in hole from 2,590 m to 2,641 m

Write short, specific descriptions. "Drill 8½ in hole from 2,512 m to 2,590 m" is far more useful than "continue drilling".

Recording NPT

NPT (non-productive time) is time when operations make no planned progress. Examples include rig equipment repairs, waiting on weather, stuck pipe, and lost circulation. Each NPT event is recorded with its cause, duration, and responsible party, because this data is used to calculate cost and improve planning for the next well.

Common mistakes

  • Total hours do not add up to 24.
  • The depth in the header does not match the last depth in the time breakdown.
  • NPT is booked as a normal activity, so it disappears from the summary.
  • Mixed units, such as metres and feet in one report.
  • A 24-hour plan so general that it cannot be compared with the next day's results.

Practice writing a DDR

The best way to understand a DDR is to write one yourself from well data. DrillSight includes demo wells with weeks of daily reports to practise on, with a Personal / Academic source-code licence from Rp150,000, one-time.