How to write a Daily Drilling Report: structure, terms and an example
A Daily Drilling Report (DDR) is the official record of what happened on a well over 24 hours. It is sent to the operator's office every morning and is the basis for tracking progress, cost, and problems on the well. For petroleum engineering students, understanding the DDR is a fast way to learn how drilling operations run day to day.
Who writes the DDR
The DDR is usually compiled by the drilling supervisor (often called the company man) with help from the wellsite drilling engineer. The data comes from many people: the rig crew for hourly activities, the mud engineer for mud data, the directional driller for surveys, and the mud logger for depth and gas data.
The usual structure of a DDR
Every company has its own format, but the content almost always includes the following sections.
| Section | Content |
|---|---|
| Header | Well name, rig, report number, date, days from spud, MD and TVD |
| 24-hour summary | A short summary of the work completed |
| Time breakdown | Activities per time period with operation codes and depths |
| NPT | Non-productive time, its cause, and its duration |
| Mud data | Density, viscosity, PV, YP, filtrate, and volume |
| BHA and bits | Bottom hole assembly, rotating hours, and bit condition |
| Surveys | Depth, inclination, and azimuth |
| HSE and personnel | People on site, incidents, and safety drills |
| 24-hour plan | Work planned for the next day |
Writing the time breakdown properly
The time breakdown is the most-read part of the report. The basic rules are simple: durations must add up to exactly 24 hours, every line has an operation code, and start and end depths are recorded for activities that make hole.
| Time | Code | Description |
|---|---|---|
| 00:00–06:00 | DRL | Drill 8½ in hole from 2,512 m to 2,590 m |
| 06:00–07:00 | CIRC | Circulate bottoms up before survey |
| 07:00–07:30 | SRV | Survey at 2,585 m, inclination 38.4° |
| 07:30–09:00 | NPT | Top drive repair |
| 09:00–12:00 | DRL | Drill 8½ in hole from 2,590 m to 2,641 m |
Write short, specific descriptions. "Drill 8½ in hole from 2,512 m to 2,590 m" is far more useful than "continue drilling".
Recording NPT
NPT (non-productive time) is time when operations make no planned progress. Examples include rig equipment repairs, waiting on weather, stuck pipe, and lost circulation. Each NPT event is recorded with its cause, duration, and responsible party, because this data is used to calculate cost and improve planning for the next well.
Common mistakes
- Total hours do not add up to 24.
- The depth in the header does not match the last depth in the time breakdown.
- NPT is booked as a normal activity, so it disappears from the summary.
- Mixed units, such as metres and feet in one report.
- A 24-hour plan so general that it cannot be compared with the next day's results.
Practice writing a DDR
The best way to understand a DDR is to write one yourself from well data. DrillSight includes demo wells with weeks of daily reports to practise on, with a Personal / Academic source-code licence from Rp150,000, one-time.